Step 1. Install steel footings on level concrete foundations.
Step 2. Align galvanized steel panel to be pre-assembled.
Step 3. Place rubber sealant from ready-to-use roll between panels.
Step 4. Connect panels with bolts and nuts.
Step 5. Position bottom panel sections,and finish up base of tank.
Step 6. Position three sides of the tank.
Step 7: Position and fix roof panels and if required ,roof support pipes and plates.
Step 8: Install reinforcement if required.
Step 9: Close up the tank with the fourth side.
Step 10.Finish the internal or external reinforcement.