Aluminum Ceiling Tile Installation Process

Author:goodwillmetalwork 2020-08-06 10:56:45 324 0 0

Metal ceilings originate from Europe, America, and other countries. Ten years ago, aluminum ceilings tile for decoration were regarded as high-end products. Today, metal aluminum ceilings panels have entered thousands of households.

Why are some aluminum ceilings panels installed with large gaps between the panels, and some panels are installed, and the ceiling shows unevenness? The corners of high-quality professional gussets are generally close to right angles, and the hemming size is uniform. In this way, after the precise clamping position between the keel and the gusset plate, the gusset plate and the gusset plate will fit closely, thereby avoiding the phenomenon of looseness and excessive gaps. If you want to have a perfect integrated ceiling, seven points are reflected in the installation process.

Installation process

1. Weak line: According to the floor elevation level, according to the design elevation, set the ceiling elevation level along the walls around the wall, and find the center point of the room, and along the ceiling elevation level, draw the keel division on the wall with the room center point as the center Location line.

2. Install the main keel boom: After the ceiling elevation level and the keel position line are played, determine the elevation of the lower end of the boom, install the pre-processed boom, and fix the boom on the ceiling with a diameter 8 expansion bolt. The boom is made of round steel with a diameter of 8 and the spacing of the suspension bars is controlled within the range of 1200 mm.

3. Install the main keel: C38 light steel keel is generally used for the main keel, and the spacing is controlled within the range of 1200 mm. During installation, the hanger matched with the main keel is connected with the boom.

Aluminum Ceiling Tile

4. Install the side keel: Fix the 25×25㎜ paint keel with cement nails around the wall according to the ceiling height requirements, and the distance between the cement nails is not more than 300 mm.

5. Install the secondary keel: According to the specifications and dimensions of the aluminum ceiling, install the secondary keel that matches the board, and the secondary keel is hung on the main keel through a hanger. When the length of the secondary keel needs to be extended by multiple keels, use the secondary keel connector to connect the opposite ends while hanging the secondary keel, and straighten it before fixing.

6. Install the metal plate: When installing the aluminum ceiling, pull a reference line perpendicular to the secondary keel in the middle of the assembly area, and align the reference line to install on both sides. When installing, handle with care, and press the two sides of the square plate in the order of the flanging position, and then push it tightly after snapping into the keel.

7. Cleaning: After the aluminum ceiling is installed, wipe the surface of the board with a cloth, and there should be no dirt and fingerprints.

8. The following documents and records should be checked during the acceptance of the suspended ceiling project:

① Construction drawings, design instructions and other design documents of the ceiling project;

②Product qualification certificate, performance test report, field acceptance record and re-inspection report of materials;

③Concealed project acceptance record;

④ Construction records.

The above information is provided by aluminum strip ceiling factory.