MPP power pipe construction, the first thing to do is to carry out pre-buried work, that is, the pipe is buried in the ground, or can be laid in the wall, so as to better protect the role of cable and wire, and in any environment can be constructed, of course, in the surrounding environment is better to use the effect will be better. But the process of construction is often bumped, broken and other problems arise, seriously affecting the quality of construction. In order to prevent the emergence of certain problems, it is necessary to pay more attention to some things when the construction of the construction staff.


MPP power pipe in the construction of what matters should be noted?cid=5


1. Welding surface pipe, the wrong side of the pipe wall thickness of no more than 10%. Hot melt machine clamps in the pipe diameter arc with a gap, through the pad to protect the MPP power pipe coaxiality will lead to welding misalignment, be sure to protect the pipe direct standard and hot melt machine clamps standard.

2. When the temperature is low, the heating temperature should be raised and the heat absorption time should be extended. Increase the heating temperature and extend the heat absorption time, when the ambient temperature is lower than -5 ℃ or windy weather, there should be insulation and preventive measures. The welding port has a greater relationship between the manipulation of temperature and the environment.

3. The heating pressure should be controlled in stages, with a slightly higher pressure when heating and a smaller pressure when absorbing heat. Rainy weather can not be MPP pipe welding, otherwise welding pipe end face will produce water vapor, before heating, you need to bake the pipe face with heating plate until the water vapor completely evaporated, and then pipe heating.

4. When the ambient temperature is lower than - 5°C or windy weather, there should be insulation and preventive measures. Otherwise, the welding quality will be seriously affected.

MPP power pipe heating plate surface and pipe end should be cleaned with alcohol frequently to ensure that the heating plate surface is free of oil and water and impurities.

6. Weld cooling should be natural cooling, the use of forced cooling, will affect the quality of pipe welding.

7. The anti-adhesive layer on the surface of the heating plate should be undamaged. Before welding, a clean rag should be used to wipe the water, impurities and soil from the pipe end surface. The welded pipe end surface should be kept clean.

8. When there is water vapor on the end face of the pipe to be welded, the heating plate should be used to bake the end face of the pipe until the water vapor is completely removed before heating the pipe.

9. When cleaning the end face of the pipe, someone should supervise the pipe to prevent the pipe from hurting your hands.

10. When the wall thickness of the pipe is less than 6mm, hot melt butt jointing is generally not used. Otherwise, it is difficult to ensure the quality of pipe welding.