Nowadays, various container houses have appeared, and they are widely used in different places. This is the case for container offices, regarding the construction process of container offices.
1. Construction process laying out-excavating foundation trench-C15 concrete foundation ground beam and ground concrete cushion construction-ground beam installation-column installation-floor in-line beam system installation-walkway system installation-outside Wall panel installation-window installation-door installation-canopy system installation-roof system installation-internal partition wall installation-PVC ceiling-cleaning site-completion acceptance
2. Construction requirements 1. Gray line stakeout: Measure according to the location of the floor plan of the living area. Residential container components The installation position of each component should meet the design requirements, and the location of the on-site welding parts should be accurate, without false welding or missing welding.
fastener
a. Fasteners should comply with GB5782 regulations
b. The bolts need to be installed in the correct position and filled with washers according to the design requirements, and must not be installed or missing.
C. The connecting bolts between components need to be tightened.
Paint
a. A layer of anti-rust paint should be repainted at the place where the primer peels off during on-site welding and transportation
b. Two coats of topcoat should be applied to the exposed parts of the components, and the paint must not have the phenomenon of missing brushing, peeling, hanging paint and returning rust.
Wall
a. According to the layout plan, the container office and wall should be corrected. The corners and external corners of the umbrella wall are sealed with angle aluminum. The connection between the board and the board is made of I-shaped aluminum. The walls must be vertical and caulked. The depth should be the same, neat and clean, the wall should be clean, the color should be the same, the board seam should be neat, the nailing surface should be consistent up and down, and there should be no dislocations, and the necessary parts should be self-tapping bolts.
b. Mark the position of the doors and windows of the container conference room according to the design drawings, cut out the position of the door and window holes with a cutting machine, install the windows and doors according to the position of the door and window holes, the windows are plastic-steel windows, and the container mobile room leases the bottom ceiling.
Our company also has Container House on sale, welcome to contact us.